Keystone at Wooster Heights Breaks Ground

Yesterday’s groundbreaking on our senior living community project was a festive occasion; turnout included Mayor Mark Boughton, members of the Greater Danbury Chamber of Commerce, and those who have already reserved their spots in the new community, as well as members of the Danbury community. The project, the first of its kind in Danbury, comprises 55 apartments those who do not require any living assistance, 63 units for those with varying assistance needs, and 22 apartments for people living with Alzheimer’s disease and dementia who require ongoing monitoring and care. The community will include a library, theater, pub, ice cream parlor, salon and activity rooms.

For more information, go to https://keystoneplaceatwoosterheights.com/.

Bethel Schools Project Ramping Up
1.jpg

The arrival of the first of 12 temporary classrooms marks an important project milestone of the Rockwell School project. The classrooms will become fully functional over the next 4 to 6 weeks, ready for the start of 2019-2020 school year. The temporary classrooms will hold students from areas being renovated within the building; as an area is completed, the students will move back and another space will undergo renovation with those students moved to the temporary classrooms.

Bethel Schools Groundbreaking A Success

Thursday’s groundbreaking ceremony in recognition of the Anna H. Rockwell & M. T. Johnson Elementary Schools Additions and Renovations projects was, in every sense, a success! The Bethel community joined us along with the Bethel school administrators, building committee, and students, and we had a memorable day on all sides. Thank you to everyone who came out; we are so excited to be working on this project in our own backyard!

Stay tuned for more project updates!

The Rockwell & Johnson Elementary Schools Groundbreaking
Invitation v5 digital.jpg

Bethel Public Schools, the Town Of Bethel - CT, and Rizzo Corporation invite you to attend the groundbreaking ceremony in recognition of the Anna H. Rockwell & M. T. Johnson Elementary Schools Additions and Renovations projects.

The ceremony will be held in Johnson's side parking lot and will include photo opportunities as well as addresses by key individuals of the projects. The rain date for this event is April 23rd at 11 am.

Please email pares@bethel.k12.ct.us with any questions.

We can't wait to see you!

Rizzo, Bethel Settle GMP for Bethel Schools Projects
Google Earth Aerial 2.JPG

Over the past year, the Rizzo Corporation, the Bethel Public Site and Building Commission, State of Connecticut Department of Administration Services, and the design team from Perkins Eastman have been working together to develop a project that satisfies the customers education objectives and falls within the approved budget. The end result of the pre-construction process is the presentation for acceptance of the Rizzo Guaranteed Maximum Price (GMP).

Prior to the GMP, Perkins Eastman developed documentation at three stages of design. Each design stage represents a higher level of completeness starting with schematic design (SD), continuing with design development (DD), and ending with construction documents (CD). At each design stage, the Rizzo pre-construction team, lead by Ed Barrett and Ron Cassella, performed constructability reviews, value engineering evaluations, schedule development, and a detailed budget. Recommendations were presented to the commission prior to moving to the next stage. With the issuance of the construction documents and with the approval of the Department of Administrative Services and the Bethel Public Site and Building Commission, the Rizzo Corporation as Construction Manager advertised the projects for subcontractor bids. Each project included over thirty bid packages. Once the bids were received and evaluated, the apparent low bidders were interviewed to make sure all the requirements were met, they fully understood the project schedule, and included all the work scope within their proposal.

Once the Rizzo Corporation was satisfied the contractors were properly vetted and confident in their abilities, the GMP was developed and presented to the Building Commission and Bethel Town Officials for approval.

Why does any of this matter? Our Guaranteed Maximum Price locks in the project construction costs. Rizzo is responsible for cost overruns, unless the GMP has been increased via a formal change order. Project contingencies are included in the GMP to cover the inevitable unforeseen conditions and the unused funds will be returned to the Town of Bethel.

 